AEG Electrolux EFT 520 Operations Instructions Page 31

  • Download
  • Add to my manuals
  • Print
  • Page
    / 38
  • Table of contents
  • BOOKMARKS
  • Rated. / 5. Based on customer reviews
Page view 30
31
If the Thyrobox VR is only to be temporarily shut down then the following steps are necessary for
decommissioning.
The decommissioning of the Thyrobox VR refers to fig. 12 Block diagram Thyrobox VR and Cable
Distribution Cabinet.
13.1 SEQUENCE OF DECOMMISSIONING
ATTENTION
Danger of short circuit
F30 in the cable distribution cabinet and F1 in the Thyrobox VR must not be closed simultaneously,
otherwise there is a short circuit.
ATTENTION
Danger of short circuit when not adhering to the sequence of the following steps.
ATTENTION
Danger of network fall out (PV side) through tripping fuses F30 when not adhering to the switching
sequence.
For decommissioning the Thyrobox VR the following steps are required:
1. Open fuse load switch F1 (125 A) Thyrobox VR
2. Close F30 cable distribution cabinet
3. Open F10 and F20 cable distribution cabinet
Status of the Thyrobox:
The Thyrobox VR is now free of voltage and bypassed, which means voltage regulation is no
longer taking place, utility (EVU) and PV side are connected directly with one another via F30
(cable distribution cabinet).
With these steps the decommissioning for the purpose of temporary (short term) shutdown is
completed. If the Thyrobox VR is to be shut down for a longer period then further measures are
required (see also Chapter Storage and Chapter Disassembly).
13. DECOMMISSIONING
Page view 30
1 2 ... 26 27 28 29 30 31 32 33 34 35 36 37 38

Comments to this Manuals

No comments